Emerson HAS8xE-IM-ATEX TV Converter Box User Manual


 
MLT 2 / BINOS
100 F
Emerson Process Management Manufacturing GmbH & Co. OHG2 - 16
ATEX Instruction Manual
HAS8xE-IM-ATEX
January 2004
2-7-2 Mains Connection
The mains power line cord has to be
connected to the terminals provided at the
analyzer enclosure’s inner left side, near the
EMC line filter (fig. 2-5).
Fig. 2-5
Terminal location inside analyzer
Terminals
EMC line filter
Verify that the mains voltage
at the point of installation
meets the analyzer nominal
voltage!
2-7-2-2 Analyzer
The pre-purging sequence can be refrained
if it is ensured that at the moment of
activating the analyzer the atmosphere
inside the enclosure and the appropriate
pipes is well below 25 % LEL.
It is the responsibility of the
user to omit pre-purging!
By default the analyzer has to be supplied
separatly to the pressurization unit. This
Omitting the pre-purge sequence
allows to shut on the safety device for pre-
purging the analyzer, while this is still shut
off!