LSI AA1167-E1 TV Mount User Manual


 
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . About this Site Preparation Guide
72-Inch Cabinet Site Preparation and Installation Guide 1
About this Site Preparation Guide
This document is intended for service technicians. It contains site preparation
requirements and instructions for installing a 72-inch cabinet. This document also
provides instructions for transporting the cabinet to another location. These instructions
assume that the reader is knowledgeable in computer system operation, maintenance, and
repair.
Customer Responsibilities
The following list describes some of the items and equipment you must provide, plus the
facility preparations you must complete before installing a 72-inch high rackmount
cabinet:
Provide a site drawing that shows the location of the following:
Equipment currently installed at the site and the area designated for the 72-inch
cabinet installation
Existing site wiring (power, signal paths, and lengths)
Equipment capable of generating electrical noise, electromagnetic interference, and
heat
Provide and install the following items:
Required communications cables, wall jacks, special connectors, and associated
hardware
Necessary power distribution boxes, conduits, grounds, lightning protection, and
associated hardware (see "Power Requirements" on page 10)
Required auxiliary power or other equipment
Make building alterations necessary to meet wiring, environmental, and other site
requirements
Make sure all site construction, wiring, or other alterations meet applicable codes,
regulations, and laws (including, but not limited to, electrical, building, safety, and
health)
Provide necessary storage and service areas (see "Environmental Requirements" on
page 9)
Provide floor coverings and environmental systems that limit or control electricity
build-up and discharge