HP (Hewlett-Packard) HP 16510B TV Converter Box User Manual


 
A
Installing New Logic Analyzer Boards
into the Mainframe
Introduction This appendix explains, how to initially inspect the HP 16510B
State/Timing Module, how to prepare it for use, storage and shipment.
Also included are procedures for module installation.
Initial
Inspection
Inspect the shipping container for damage. If the shipping container or
cushioning material is damaged, it should be kept until the contents of the
shipment have been checked for completeness and the module has been
checked mechanically and electrically. The contents of the shipment
should be as listed in the "Accessories Supplied" paragraph in Chapter 1.
If the contents of the container are incomplete, there is mechanical damage
or defect, or the instrument does not pass the performance tests, notify the
nearest Hewlett-Packard office. Procedures for checking electrical
performance are in Section III of the HP 16510B Service Manual.
If the shipping container is damaged, or the cushioning material shows
signs of stress, notify the carrier as well as the Hewlett-Packard office.
Keep the shipping material for the carrier’s inspection. The
Hewlett-Packard office will arrange for repair or replacement at
Hewlett-Packard’s option without waiting for claim settlement.
Power
Requirements
All power supplies required for operating the HP 16510B State/Timing
Module are supplied to the module through the backplane connector of the
HP 16500A Logic Analysis System mainframe.
HP 16510B Installing New Logic Analyzer Boards into the Mainframe
Front-Panel Reference A-1