Lucent Technologies 555-233-119 Home Theater Server User Manual


  Open as PDF
of 1872
 
DEFINITY ECS Release 8.2 Maintenance for R8.2csi
555-233-119 Issue 1
April 2000
Maintenance Objects
3-455DAT-LINE (Data Line)
3
Conference Circuit Test (#7)
The Conference Circuit Test verifies that the NPE channel for the port being
tested can correctly perform the conferencing function. The NPE is instructed to
listen to several different tones and conference the tones together. The resulting
signal is then measured by a Tone Detector port. If the level of the tone is within a
certain range, the test passes.
Audit Update Test (#36)
This audit makes sure that the hardware state of the Data Line is consistent with
the system translations. When this audit is run, the port is queried for the
switchhook state, and the software state is updated according to the returned
value. Also, the data line options are sent down to the port.
Table 3-193. TEST #7 Conference Circuit Test
Error
Code
Te st
Result Description/Recommendation
ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals a maximum of 5 times.
1000 ABORT System resources required to run this test are not available. The port may
be in use on a valid call. Use status data-module to determine when the
port is available for testing.
1004 ABORT The port has been seized by a user for a valid call. Use status
data-module to determine when the port is available for testing.
1. Retry the command at 1-minute intervals a maximum of 5 times.
1020 ABORT The test did not run due to an already existing error on this port (Error Type
769).
1. Refer to the procedure for Error Type 769. If Error Type 769 still occurs
on this port, replace the circuit pack.
2000 ABORT Response to the test request was not received within the allowable time
period.
2100 ABORT Could not allocate the necessary system resources to run this test.
1. Retry the command at 1-minute intervals a maximum of 5 times.
Any FAIL The conference circuit test failed (possible off-board problem).
1. Busyout and release the port (data line), and then retest.
2. Replace the circuit pack if the test continues to fail.
PASS The port can correctly conference multiple connections. User-reported
troubles on this port should be investigated using other port tests,
examining the ADU, external wiring, and customer equipment.
Continued on next page