Lucent Technologies 555-233-119 Home Theater Server User Manual


  Open as PDF
of 1872
 
DEFINITY ECS Release 8.2 Maintenance for R8.2csi
555-233-119 Issue 1
April 2000
Maintenance Objects
3-1047TBRI-PT (TN2185 ISDN Trunk-Side BRI Port)
3
1 FAIL Received a status of Level 1 Pending Activation. U interface down
indicating a problem with a connection between the switch and the NT1, a
2- to 4-wire converter that is used to connect 4-wire terminals to a 2-wire
TN2198 or TN2185 circuit pack.
1. Verify that the connections between the switch and the NT1 are good.
Verify that the NT1 has power.
2. Execute the test port PCSSpp command and review the results of the
Level 1 Status Inquiry Test to verify the repair. If this test still fails,
proceed to Step 3.
3. Follow the manufacturers repair procedures for the NT1. Then execute
the test port PCSSpp command and review the results of the Level 1
Status Inquiry Test to verify repair.
2 FAIL Received a status of Level 1 Pending Activation. U interface up, S/T
interface down, which indicates a problem with the NT1 or the wiring
between the NT1 and the BRI endpoint (S/T interface).
1. Execute the test port PCSSpp command and review the results of the
Level 1 Status Inquiry test to verify the repair. If this test still fails,
proceed to Step 2.
2. Follow the manufacturer-recommended repair procedures for the NT1.
Then execute the test port PCSSpp command and review the results
of the Level 1 Status Inquiry test to verify repair.
3 FAIL Received a status of Level 1 Deactivated; the port is out-of-service.
1. Issue the status bri-port PCSSpp command to verify that the service
state of the port is out-of-service. If the service state of the port is not
out-of-service, proceed to Step 2.
2. If the port has been placed out-of-service with the busyout port
PCSSpp command, try releasing the port by executing the release
port PCSSpp command. Then issue the test port long PCSSpp
command and review the results of Level 1 Status Inquiry test. If this
test still fails, proceed to Step 3.
3. After executing the test port long PCSSpp command, review the
results of all the tests. Follow the repair procedures for any tests that
fail. Verify repair of the problem by executing the test port PCSSpp
command and by determining that the Level 1 Status test passes.
Table 3-464. TEST #1242 Level 1 Status Inquiry — Continued
Error
Code
Te s t
Result Description/ Recommendation
Continued on next page